SUBCHAPTER V—PUERTO RICO INFRASTRUCTURE REVITALIZATION
§2211. Definitions
In this subchapter:
(1) Act 76
The term "Act 76" means Puerto Rico Act 76–2000 (3 L.P.R.A. 1931 et seq.), approved on May 5, 2000, as amended.
(2) Critical Project
The term "Critical Project" means a project identified under the provisions of this subchapter and intimately related to addressing an emergency whose approval, consideration, permitting, and implementation shall be expedited and streamlined according to the statutory process provided by Act 76, or otherwise adopted pursuant to this subchapter.
(3) Energy Commission of Puerto Rico
The term "Energy Commission of Puerto Rico" means the Puerto Rico Energy Commission as established by Subtitle B of Puerto Rico Act 57–2014.
(4) Energy Projects
The term "Energy Projects" means those projects addressing the generation, distribution, or transmission of energy.
(5) Emergency
The term "emergency" means any event or grave problem of deterioration in the physical infrastructure for the rendering of essential services to the people, or that endangers the life, public health, or safety of the population or of a sensitive ecosystem, or as otherwise defined by section 1 of Act 76 (3 L.P.R.A. 1931). This shall include problems in the physical infrastructure for energy, water, sewer, solid waste, highways or roads, ports, telecommunications, and other similar infrastructure.
(6) Environmental Quality Board
The term "Environmental Quality Board" means the Puerto Rico Environmental Quality Board, a board within the executive branch of the Government of Puerto Rico as established by section 7 of Puerto Rico Act 416–2004 (12 L.P.R.A. 8002a).
(7) Expedited Permitting Process
The term "Expedited Permitting Process" means a Puerto Rico Agency's alternate procedures, conditions, and terms mirroring those established under Act 76 (3 L.P.R.A. 1932) and pursuant to this subchapter shall not apply to any Federal law, statute, or requirement.
(8) Governor
The term "Governor" means the Governor of Puerto Rico.
(9) Interagency Environmental Subcommittee
The term "Interagency Environmental Subcommittee" means the Interagency Subcommittee on Expedited Environmental Regulations as further described by
(10) Legislature
The term "Legislature" means the Legislature of Puerto Rico.
(11) Planning Board
The term "Planning Board" means the Puerto Rico Planning Board, a board within the executive branch of the Government of Puerto Rico established by Puerto Rico Act 75–1975 (23 L.P.R.A. 62 et seq.).
(12) Project Sponsor
The term "Project Sponsor" means a Puerto Rico Agency or private party proposing the development of an existing, ongoing, or new infrastructure project or Energy Project.
(13) Puerto Rico Agency or Agencies
The terms "Puerto Rico Agency" or "Puerto Rico Agencies" means any board, body, board of examiners, public corporation, commission, independent office, division, administration, bureau, department, authority, official, person, entity, municipality, or any instrumentality of Puerto Rico, or an administrative body authorized by law to perform duties of regulating, investigating, or that may issue a decision, or with the power to issue licenses, certificates, permits, concessions, accreditations, privileges, franchises, except the Senate and the House of Representatives of the Legislature and the judicial branch.
(14) Puerto Rico Electric Power Authority
The term "Puerto Rico Electric Power Authority" means the Puerto Rico Electric Power Authority established by Puerto Rico Act 83–1941.
(
§2212. Position of Revitalization Coordinator
(a) Establishment
There is established, under the Oversight Board, the position of the Revitalization Coordinator.
(b) Appointment
(1) In general
The Revitalization Coordinator shall be appointed by the Governor as follows:
(A) Prior to the appointment of the Revitalization Coordinator and within 60 days of the appointment of the full membership of the Oversight Board, the Oversight Board shall submit to the Governor no less than three nominees for appointment.
(B) In consultation with the Oversight Board, not later than 10 days after receiving the nominations under subparagraph (A), the Governor shall appoint one of the nominees as the Revitalization Coordinator. Such appointment shall be effective immediately.
(C) If the Governor fails to select a Revitalization Coordinator, the Oversight Board shall, by majority vote, appoint a Revitalization Coordinator from the list of nominees provided under paragraph (A).
(2) Qualifications
In selecting nominees under paragraph (1)(A), the Oversight Board shall only nominate persons who—
(A) have substantial knowledge and expertise in the planning, predevelopment, financing, development, operations, engineering, or market participation of infrastructure projects, provided that stronger consideration may be given to candidates who have experience with Energy Projects and the laws and regulations of Puerto Rico that may be subject to an Expedited Permitting Process;
(B) does 1 not currently provide goods or services to the government of Puerto Rico (and, as applicable, is 2 not the spouse, parent, child, or sibling of a person who provides or has provided goods and services to the government of Puerto Rico in the preceding 3 calendar years); and
(C) shall not be an officer, employee of, or former officer or employee of the government of Puerto Rico in the preceding 3 calendar years.
(3) Compensation
The Revitalization Coordinator shall be compensated at an annual rate determined by the Oversight Board sufficient in the judgment of the Oversight Board to obtain the services of a person with the skills and experience required to discharge the duties of the position, but such compensation shall not exceed the annual salary of the Executive Director.
(c) Assignment of personnel
The Executive Director of the Oversight Board may assign Oversight Board personnel to assist the Revitalization Coordinator.
(d) Removal
(1) In general
The Revitalization Coordinator may be removed for any reason, in the Oversight Board's discretion.
(2) Termination of position
Upon the termination of the Oversight Board pursuant to
(
1 So in original. Probably should be "do".
2 So in original. Probably should be "are".
§2213. Critical Projects
(a) Identification of projects
(1) Project submission
Any Project Sponsor may submit, so long as the Oversight Board is in operation, any existing, ongoing, or proposed project to the Revitalization Coordinator. The Revitalization Coordinator shall require such submission to include—
(A) the impact the project will have on an emergency;
(B) the availability of immediate private capital or other funds, including loan guarantees, loans, or grants to implement, operate, or maintain the project;
(C) the cost of the project and amount of Puerto Rico government funds, if any, necessary to complete and maintain the project;
(D) the environmental and economic benefits provided by the project, including the number of jobs to be created that will be held by residents of Puerto Rico and the expected economic impact, including the impact on ratepayers, if applicable;
(E) the status of the project if it is existing or ongoing; and
(F) in addition to the requirements found in subparagraphs (A) through (E), the Revitalization Coordinator may require such submission to include any or all of the following criteria that assess how the project will—
(i) reduce reliance on oil for electric generation in Puerto Rico;
(ii) improve performance of energy infrastructure and overall energy efficiency;
(iii) expedite the diversification and conversion of fuel sources for electric generation from oil to natural gas and renewables in Puerto Rico as defined under applicable Puerto Rico laws;
(iv) promote the development and utilization of energy sources found on Puerto Rico;
(v) contribute to transitioning to privatized generation capacities in Puerto Rico;
(vi) support the Energy Commission of Puerto Rico in achievement of its goal of reducing energy costs and ensuring affordable energy rates for consumers and business; or
(vii) achieve in whole or in part the recommendations, if feasible, of the study in
(2) Identification of relevant Puerto Rico Agencies
Within 20 days of receiving a project submission under paragraph (1), the Revitalization Coordinator shall, in consultation with the Governor, identify all Puerto Rico Agencies that will have a role in the permitting, approval, authorizing, or other activity related to the development of such project submission.
(3) Expedited Permitting Process
(A) Submission of Expedited Permitting Process
Not later than 20 days after receiving a project submission, each Puerto Rico Agency identified in paragraph (1) shall submit to the Revitalization Coordinator the Agency's Expedited Permitting Process.
(B) Failure to provide Expedited Permitting Process
If a Puerto Rico Agency fails to provide an Expedited Permitting Process within 20 days of receiving a project submission, the Revitalization Coordinator shall consult with the Governor to develop within 20 days an Expedited Permitting Process for the Agency.
(C) Implementation and prioritization
The Revitalization Coordinator shall require Puerto Rico Agencies to implement the Expedited Permitting Process for Critical Projects. Critical Projects shall be prioritized to the maximum extent possible in each Puerto Rico Agency regardless of any agreements transferring or delegating permitting authority to any other Territorial Instrumentality or municipality.
(b) Critical Project Report
(1) In general
For each submitted project, the Revitalization Coordinator in consultation with the Governor and relevant Puerto Rico Agencies identified in subsection (a)(2) shall develop a Critical Project Report within 60 days of the project submission, which shall include:
(A) An assessment of how well the project meets the criteria in subsection (a)(1).
(B) A recommendation by the Governor whether the project should be considered a Critical Project. If the Governor fails to provide a recommendation during the development of the Critical Project Report, the failure shall constitute a concurrence with the Revitalization Coordinator's recommendation in subparagraph (E).
(C) In the case of a project that may affect the implementation of Land-Use Plans, as defined by Puerto Rico Act 550–2004, a determination by the Planning Board will be required within the 60-day timeframe. If the Planning Board determines such project will be inconsistent with relevant Land-Use Plans, then the project will be deemed ineligible for Critical Project designation.
(D) In the case of an Energy Project that will connect with the Puerto Rico Electric Power Authority's transmission or distribution facilities, a recommendation by the Energy Commission of Puerto Rico, if the Energy Commission determines such Energy Project will affect an approved Integrated Resource Plan, as defined under Puerto Rico Act 54–2014. If the Energy Commission determines the Energy Project will adversely affect an approved Integrated Resource Plan, then the Energy Commission shall provide the reasons for such determination and the Energy Project shall be ineligible for Critical Project designation, provided that such determination must be made during the 60-day timeframe for the development of the Critical Project Report.
(E) A recommendation by the Revitalization Coordinator whether the project should be considered a Critical Project.
(2) Public involvement
Immediately following the completion of the Critical Project Report, the Revitalization Coordinator shall make such Critical Project Report public and allow a period of 30 days for the submission of comments by residents of Puerto Rico specifically on matters relating to the designation of a project as a Critical Project. The Revitalization Coordinator shall respond to the comments within 30 days of closing the coming 2 period and make the responses publicly available.
(3) Submission to Oversight Board
Not later than 5 days after the Revitalization Coordinator has responded to the comments under paragraph (2), the Revitalization Coordinator shall submit the Critical Project Report to the Oversight Board.
(c) Action by the Oversight Board
Not later than 30 days after receiving the Critical Project Report, the Oversight Board, by majority vote, shall approve or disapprove the project as a Critical Project, if the Oversight Board—
(1) approves the project, the project shall be deemed a Critical Project; and
(2) disapproves the project, the Oversight Board shall submit to the Revitalization Coordinator in writing the reasons for disapproval.
(
Editorial Notes
References in Text
1 See References in Text note below.
§2214. Miscellaneous provisions
(a) Creation of Interagency Environmental Subcommittee
(1) Establishment
Not later than 60 days after the date on which the Revitalization Coordinator is appointed, the Interagency Environmental Subcommittee shall be established and shall evaluate environmental documents required under Puerto Rico law for any Critical Project within the Expedited Permitting Process established by the Revitalization Coordinator under
(2) Composition
The Interagency Environmental Subcommittee shall consist of the Revitalization Coordinator, and a representative selected by the Governor in consultation with the Revitalization Coordinator representing each of the following agencies: The Environmental Quality Board, the Planning Board, the Puerto Rico Department of Natural and Environmental Resources, and any other Puerto Rico Agency determined to be relevant by the Revitalization Coordinator.
(b) Length of Expedited Permitting Process
With respect to a Puerto Rico Agency's activities related only to a Critical Project, such Puerto Rico Agency shall operate as if the Governor has declared an emergency pursuant to section 2 of Act 76 (3 L.P.R.A. 1932). Section 12 of Act 76 (3 L.P.R.A. 1942) shall not be applicable to Critical Projects. Furthermore, any transactions, processes, projects, works, or programs essential to the completion of a Critical Project shall continue to be processed and completed under such Expedited Permitting Process regardless of the termination of the Oversight Board under
(c) Expedited Permitting Process compliance
(1) Written notice
A Critical Project Sponsor may in writing notify the Oversight Board of the failure of a Puerto Rico Agency or the Revitalization Coordinator to adhere to the Expedited Permitting Process.
(2) Finding of failure
If the Oversight Board finds either the Puerto Rico Agency or Revitalization Coordinator has failed to adhere to the Expedited Permitting Process, the Oversight Board shall direct the offending party to comply with the Expedited Permitting Process. The Oversight Board may take such enforcement action as necessary as provided by
(d) Review of Legislature acts
(1) Submission of acts to Oversight Board
Pursuant to
(2) Finding of Oversight Board
Upon receipt of a law under paragraph (1), the Oversight Board shall promptly review whether the law would adversely impact the Expedited Permitting Process and, upon such a finding, the Oversight Board may deem such law to be significantly inconsistent with the applicable Fiscal Plan.
(e) Establishment of certain terms and conditions
No Puerto Rico Agency may include in any certificate, right-of-way, permit, lease, or other authorization issued for a Critical Project any term or condition that may be permitted, but is not required, by any applicable Puerto Rico law, if the Revitalization Coordinator determines the term or condition would prevent or impair the expeditious construction, operation, or expansion of the Critical Project. The Revitalization Coordinator may request a Puerto Rico Agency to include in any certificate, right-of-way, permit, lease, or other authorization, a term or condition that may be permitted in accordance with applicable laws if the Revitalization Coordinator determines such inclusion would support the expeditious construction, operation, or expansion of any Critical Project.
(f) Disclosure
All Critical Project reports, and justifications for approval or rejection of Critical Project status, shall be made publicly available online within 5 days of receipt or completion.
(
§2215. Federal agency requirements
(a) Federal Points of Contact
At the request of the Revitalization Coordinator and within 30 days of receiving such a request, each Federal agency with jurisdiction over the permitting, or administrative or environmental review of private or public projects in Puerto Rico, shall name a Point of Contact who will serve as that agency's liaison with the Revitalization Coordinator.
(b) Federal grants and loans
For each Critical Project with a pending or potential Federal grant, loan, or loan guarantee application, the Revitalization Coordinator and the relevant Point of Contact shall cooperate with each other to ensure expeditious review of such application.
(c) Expedited reviews and actions of Federal agencies
All reviews conducted and actions taken by any Federal agency relating to a Critical Project shall be expedited in a manner consistent with completion of the necessary reviews and approvals by the deadlines under the Expedited Permitting Process, but in no way shall the deadlines established through the Expedited Permitting Process be binding on any Federal agency.
(
Editorial Notes
Codification
Section is comprised of section 505 of
§2216. Judicial review
(a) Deadline for filing of a claim
A claim arising under this subchapter must be brought no later than 30 days after the date of the decision or action giving rise to the claim.
(b) Expedited consideration
The District Court for the District of Puerto Rico shall set any action brought under this subchapter for expedited consideration, taking into account the interest of enhancing Puerto Rico's infrastructure for electricity, water and sewer services, roads and bridges, ports, and solid waste management to achieve compliance with local and Federal environmental laws, regulations, and policies while ensuring the continuity of adequate services to the people of Puerto Rico and Puerto Rico's sustainable economic development.
(
§2217. Savings clause
Nothing in this subchapter is intended to change or alter any Federal legal requirements or laws.
(