43 USC 412: Prerequisites to initiation of project or division of project
Result 1 of 1
   
 
43 USC 412: Prerequisites to initiation of project or division of project Text contains those laws in effect on December 20, 2024
From Title 43-PUBLIC LANDSCHAPTER 12-RECLAMATION AND IRRIGATION OF LANDS BY FEDERAL GOVERNMENTSUBCHAPTER III-INSTITUTION AND CONSTRUCTION OF PROJECTS

§412. Prerequisites to initiation of project or division of project

After December 5, 1924, no new project or new division of a project shall be approved for construction or estimates submitted therefor by the Secretary until information in detail shall be secured by him concerning the water supply, the engineering features, the cost of construction, land prices, and the probable cost of development, and he shall have made a finding in writing that it is feasible, that it is adaptable for actual settlement and farm homes, and that it will probably return the cost thereof to the United States.

(Dec. 5, 1924, ch. 4, §4, subsec. B, 43 Stat. 702 .)


Statutory Notes and Related Subsidiaries

Definitions

The definitions in section 371 of this title apply to this section.